Successful start-up at the WWTP Linz-Unkel
Just a few days after commissioning of Germany's first sewage sludge carbonisation plant based on the PYREG Technology the belt drier of ELIQUO STULZ is performing strongly. The sewage sludge is dried to a dry matter content of more than 90%. As a consequence the PYREG reactor could start up in the same week.
During assembly the defined project plan was always followed and the commissioning started as planned on 29/06/2015.